Build Timeline

11/24/2017- Met w/Susan, toured model home along with Bentley and Camden. Decided on Bentley model. Signed contract the same day.

11/25/2017- Preview at Design Center to get Jesse’s input on choices.

12/01/2017- Met w/Susan again to discuss custom pricing for kitchen. Gave the go ahead to say we were ready for our final selections at Design Center.

12/06/2017- Went to design center to finalize choices.

12/07/2017- Met with lender to discuss paperwork. Everything was sent to Jesse to sign electronically.

12/13/2017- Lender Conditional Approval.

12/14/2017- Met w/Guardian Rep Nate. Signed Guardian contract.

1/5/2018- Pre-construction meeting.

1/10/2018- Appraisal Done

2/1/2018 – Broke Ground!! Scheduled appointment with Long Electric.

2/16/2018 – Forms go up for basement walls & then get poured a day later.

2/20/2018 – Forms are off!

2/21/2018 – Basement walls are sealed.

2/24/2018 – Trench is dug for pluming pipes.

2/27/2018 – Trenches around home are back filled & Long Electric Appointment.

3/1/2018 – Sims-Lohman appointment to pick out granite slabs.

3/12/2018 – Basement/garage slabs poured.

3/14/2018 – Framing Day 1

3/16/2018 – 2nd floor done being framed.

3/19/2018 – Trusses start to go up

3/21/2018 – Roof framing done

3/23/2018 – Prepping roof for shingles

3/24/2018 – Shingles on roof done

3/26/2018 – Mechanical stage starts. HVAC places vents in floor and ceiling.

3/30/2018 – Most of the windows & front door have been installed.

4/09/2018 – Brick has been delivered.

4/13/2018 – Pre-drywall meeting

4/20/2018 – Drywall has been hung!

4/22/2018 – Garage installed and mudding started.

4/28/2018 – Brick started and finished, textured ceiling done.

5/05/2018 – Kitchen cabinets, stair baluster, railing, siding started.

5/08/2018 – Bathroom tiling started.

5/10/2018 – LVT installed on main floor.

5/11/2018 – Kitchen granite installed.

5/13/2018 – Siding completed

5/15/2018 – Driveway and sidewalks prepped, lighting/electric outlets installed.

5/20/2018 – Lighting installed in master bathroom, toilets installed, counters/cabinets.

5/24/2018 – Driveway/sidewalks poured. Patches made to drywall.